Eskom on Friday lowered load-shedding to Stage 1 and announced that it was suspending the power outages from midnight.
“‘Eskom is pleased to announce that load-shedding will be implemented at Stage 1 load-shedding at 16:00 – 24:00 this evening,” the power utility said.
“Load-shedding will then be suspended as the generation system has recovered sufficiently at this point.
Eskom thanked the public and all stakeholders for their patience and understanding during this difficult period of load-shedding.
“While we are able to suspend load-shedding at this point, Eskom cautions that the power system constraints continue to persist,” said the power utility ahead of the weekend.
“We urge the people of South Africa to continue using electricity sparingly. Should there be any further changes, Eskom will promptly communicate and implement any changes as may be required.
“We currently have 3 693MW on planned maintenance, while another 14 261MW of capacity is unavailable due to breakdowns.”
Eskom reiterated that load-shedding was implemented only as a last resort to protect the national grid.
“We, therefore, urge all South Africans to continue using electricity sparingly, especially during these uncertain times on the power system,” said Eskom.