Johannesburg – Eskom suspended load-shedding early Sunday morning.
“Load-shedding was suspended at 01:35 this morning,” the power utility said on Twitter.
“The pumped storage dam levels have been adequately replenished for the week ahead.”
Eskom added: “Diesel levels at the OCGT power stations have improved but remain low.
“Therefore, Stage 2 load-shedding will be implemented from 08:00 until 16:00 today, followed by Stage 4 load-shedding until 05:00 on Monday.”