Johannesburg – Eskom ramped up load-shedding to Stage 3 and Stage 4 on Friday after six generating units were shut down.
“Due to further setbacks resulting in the shutdown of six generating units, as well as the delay in returning three generating units to service, Stage 3 load-shedding will be implemented at 16:00 on Friday afternoon,” Eskom said in a Power Alert.
“This will be followed by Stage 3 load-shedding from 05:00 on Saturday until 16:00 when Stage 4 load-shedding will be implemented.
“This pattern of Stage 3 load-shedding from 05:00 to 16:00 and Stage 4 load-shedding from 16:00 to 05:00 will continue until Sunday when Eskom will share a further update for the week ahead.”
The power utility said it will closely monitor the system and communicate any changes should it be required.
“Unplanned outages are currently at 15 561MW of generating capacity, while the capacity out of service for planned maintenance is 7 828MW,” said Eskom.
“Eskom Power Station General Managers and their teams are working tirelessly to ensure that 1 960MW of generating capacity is returned to service by Monday evening.”
Eskom said its load forecast for the evening peak demand for Friday was 25 169MW.
“We would like to thank those who do heed the call to use electricity sparingly and efficiently, including switching off geysers and pool pumps from 17:00 to 21:00,” the power utility said.
“This lowers demand and helps in alleviating the pressure on the power system and contributes to lower stages of load-shedding.”