Johannesburg – Eskom is suspending load-shedding this morning, Monday, (19 February 2024).
In a power alert, Eskom said, “Load-shedding will be suspended from 5:00 until 16:00 on Monday”.
However, the power utility said: “Load-shedding will resume with Stage 2 from 16:00 today until 05:00 on Monday”.
Stage 2 load-shedding will be implemented again from 16:00 on Monday until 05:00 on Tuesday.
“This alternating pattern of suspending load-shedding from 05:00 until 16:00 and Stage 2 load-shedding from 16:00 until 05:00 will be repeated daily until further notice,” Eskom said.
“While the available generation capacity has been sustained, the need to replenish the emergency reserves for the upcoming week necessitates an increase in the stage of load-shedding.”
Eskom said it will closely monitor the power system and communicate any changes to load-shedding should it be required.
“Unplanned outages have further reduced to 13 350MW of generating capacity, while the capacity out of service for planned maintenance is at 8 476MW,” the power utility said.
Eskom said Power Station General Managers and their teams were working to ensure that additional generating capacity is recovered by bringing units on unplanned outages and planned maintenance back to service.
“A total of 3 300MW of generating capacity is anticipated to be returned to service by Monday,” the power utility said.
“Eskom’s evening peak demand tonight is 24 979MW.
“We would like to thank those who do heed the call to use electricity sparingly and efficiently, including switching off geysers and pool pumps from 17:00 to 21:00 or when the load is limited.
“This lowers demand and helps in alleviating the pressure on the power system, contributing to lower stages of load-shedding.”