Johannesburg – Eskom has escalated load-shedding to Stage 6 from noon today owing to more breakdowns of generation units.
“Stage 6 load-shedding will be implemented from 12:00 until further notice,” Eskom announced in a power alert at 11h30 today.
“This is due to a high number of breakdowns since midnight, as well as the requirement to strictly preserve the remaining emergency generation reserves.”
Eskom said Stage 6 load-shedding will continue until Friday morning at 05h00, where after will be reduced to Stage 5 until Saturday morning.
The struggling power utility said since Tuesday night, breakdowns of two generating units at Grootvlei Power Station occurred, as well as a unit each at Arnot, Duvha, Kendal, Kriel, and Tutuka power stations.
“In addition, two units at Arnot, a unit each at Camden, Kendal, and Kriel power stations have been delayed in returning to service,” said Eskom.
“A unit at Matla Power Station returned to service late last night. We currently have 4 984MW on planned maintenance, while another 19 052MW of capacity is unavailable due to breakdowns.”
Eskom said due to the depletion of the budget to acquire diesel for the Open Cycle Gas Turbines, it has been “forced to strictly preserve the remaining diesel for any extreme emergency situations such as multiple, simultaneous trips of generators”.
The power utility added: “The pumped storage dam levels also need to be replenished during this load-shedding”.
Eskom said the refueling and maintenance outage started Wednesday night.
However, the power utility said the long-term operation project of Unit 1 of the Koeberg Nuclear Power Station, together with the October chimney failure – that has forced three generation units offline at Kusile Power Station – will further reduce available generation capacity and exacerbate the occurrence of load-shedding over the next six to 12 months.
Eskom requested the public to “exercise patience and tolerance during this difficult period”.
“Load-shedding is implemented only as a last resort in view of the shortage of generation capacity and the need to attend to breakdowns,” said Eskom.