A burst underground sewer pipe has stopped City Power’s work to restore electricity to the Johannesburg central business district.
Parts of the CBD had been without electricity since Monday morning when an underground fire burnt supply cables.
Earlier on Thursday, City Power estimated that repair work to restore electricity supplies could be completed by the end of the weekend.
However, hours later, Spokesperson Isaac Mangena said: “City Power’s work to clear the underground tunnels and start with repairs hit another snag when a sewerage pipe burst underground”.
He added: “The sewerage has started flooding the tunnel where mop-up work is underway after it burst around 16h45.”
Mangena said Joburg Water has been informed to attend to the sewerage.
The spokesperson said City Power has put its work on hold until the tunnel has been cleared.
“This further delays our operation which was extended by the mop-up taking longer than anticipated,” said Mangena.
“We are waiting for Joburg Water to advise us on how long the work on the sewerage pipe would take before revising our weekend ETR (estimated time of restoration).
“A preliminary assessment suggests that they will be done in two hours, if all goes according to plan.
“We really apologise to the affected customers for the inconvenience caused.”